Valley
High School
The Hansen
Company completed 5 separate general bid package contracts
over a 3 year period for this multi- phased $30 million
renovation and addition project. The first project was
a 75,000 sf classroom addition which included the creation
of new student and field house commons areas and renovation
to many existing spaces. Hansen’s scope included
the footings, slab on grade and deck, millwork, doors
and hardware, site concrete and landscaping packages.
Other contracts covered work for remodeling the gymnasium
flooring and seating, kitchen and air conditioning improvements
and the reconstruction of the exterior façade
after a one story classroom wing was demolished. All
contracts totaled approximately $5.4 million. This project
was completed while the building was occupied by students
and faculty.
Owner: West Des Moines
Public Schools
Architect: RDG Planning & Design,
Phil Hodgin
Project Team:
- Kevin Anderson, Project Manager
- Paul Edenburn, Project Superintendent




|